Do You Need Building Consent for Solar Panels in NZ?

The 40m² Rule and When Engineering Applies

Most New Zealand homes do not need building consent for rooftop solar. Since 23 October 2025, roof-mounted arrays up to 40m² can generally be exempt when the site is in a Low, Medium or High wind zone.

That is the straight answer. The fuller answer depends on your array size, wind exposure and how the panels are fixed to the roof. You have picked the panels, pictured smaller power bills; then someone mentions council consent. Fair enough to panic a little. The good news is that it is usually simpler than it sounds. Exempt does not mean anything goes, though.

Clause 28D of Schedule 1 of the Building Act 2004 covers the straightforward route. Building consent is generally not needed when:

  • The total array area is 40m² or less

  • Panels are mounted on a structure with structural fixings to the roof

  • The site has a design wind speed of 44 metres per second or less

  • Panels meet applicable setback requirements from roof edges and gutters

  • The array does not extend beyond the roofline

A typical panel is roughly 2m², so 40m² may be around 20 panels. Roughly. Panel dimensions and layouts vary, so the proposed design needs proper measuring. This is not permission to fill every spare inch of roof with glass and call it a day.

Arrays over 40m² can still avoid consent under Clause 48A. The same applies where design wind speeds exceed 44 metres per second. The difference is engineering. A Chartered Professional Engineer, or CPEng, must design or review the structural fixings, with the installation following that design. The other recognised route is a pre-engineered kitset with unified CPEng sign-off.

A quick glance at the roof followed by “she’ll be right” is not engineering. If neither route applies, building consent may be needed.

Wind Zones, Roof Structures and the Checks That Remain

New Zealand wind zones run from Low to Extra High. Low, Medium and High sites may use the under-40m² exemption. Very High and Extra High sites move onto the CPEng route, whatever the array size.

Two homes in the same suburb can have different requirements. Elevation, terrain, exposure and nearby buildings can all affect the answer. Council maps are useful starting points, but your section needs assessing on its own facts.

Trying to split panels into smaller groups on one roof does not automatically reset the 40m² count either. The limit applies to the total array area on each independent roof structure. A separately framed garage may be treated differently, depending on how it is supported. That is a design question to settle early. Not after you have chosen an installer.

Building consent exemption also does not remove other obligations. The work must still meet the Building Code, exemption conditions and relevant District Plan rules. The roof needs to remain structurally sound and weathertight around every fixing.

Other items worth checking include:

  • Resource consent where heritage, special character or planning rules apply

  • Integrated solar roofing, where panels form part of the roof cladding rather than sit on frames

  • Electrical work completed and certified by a licensed electrical worker

  • Approval from your local lines company before grid connection

A Consistent Brief Makes Quotes Easier to Compare

This is where quote comparisons can get messy. Without a proper rooftop solar design first, each installer may work from different assumptions about panel numbers, roof layout, wind exposure, fixings and engineering. That is not comparing apples with apples. It is comparing apples to lawnmowers.

Our approach is calmer. We work through the design first, then procure up to three quotes from qualified SEANZ installers against the same brief. No favourites. No preferred suppliers. No under-the-table dealings. We serve you, not sales targets.

Where an engineering or consent question needs more attention, we can flag it. We do not replace an engineer, council or insurer. Our job is to make sure important questions are not brushed aside by a commissioned salesperson keen to get a deal signed.

The service is free for you. We are paid by the installer when a job goes ahead. Our published fee is 8% to 10% for residential jobs and 5% to 7% for commercial jobs. That gives us every reason to help you land the right system, a competitive price and an installer you trust, so the project can proceed without unnecessary stress.

Get Rooftop Solar Quotes Without The Sales Pressure

Use our rooftop solar calculator to get a clearer starting point before you speak to installers. Equity Solar Brokers can then procure up to three quotes from qualified SEANZ installers, with no favourites and no mucking about. We serve you, not sales targets. Ready to compare properly? Contact us for a no-pressure chat.

FAQs

Do New Builds And Commercial Properties Qualify?

Yes. These roof-mounted solar exemptions can apply to new and existing buildings, including homes and commercial properties, provided the relevant conditions are met. The property type does not remove the need to assess the roof structure, array area, wind zone and fixings.

Do I Still Need Electrical Certification And What About Insurance?

Yes. No building consent does not mean no electrical paperwork. A licensed electrical worker must complete and certify the electrical work, and your lines company must approve grid connection. Insurance outcomes depend on your policy and the circumstances of any claim. Compliance issues may complicate matters, so keep your solar design, any engineering information and electrical certificates with your house records. This is general information only. Check current MBIE guidance and seek appropriate professional advice for your specific project.